Progress construction Feringa Building › Campus Groningen

Progress construction Feringa Building

Progress construction Feringa Building

Progress construction Feringa Building

Tue, 6 October 2020

The progress of the construction of the Feringa Building of the University of Groningen on Zernike Campus cannot be missed! Read all about the steady progress in this article that was published recently by the UG. 

Feringa Building rises above ground

Anyone walking past the Feringa Building project at the University of Groningen at Zernike before the summer holiday will only have seen foundation work being carried out. Now, however, the first steel structures and constructional walls of this new University building are clearly visible, rising above the ground. In addition, the German company Wesemann has been commissioned to furnish the laboratories. Building Phase 1 of the Feringa Building started in mid-2019 and is going according to plan. In consultation with the contractors, the current building schedule has been extended by approximately six months. The first phase will now be ready for use by mid-2022. See the explanation further on. Follow the building work online via a web cam.

Once more than 2,000 foundation piles had been driven into place under the Feringa Building in early 2020, the next six months were spent on the entrance to the underground bike park, the main lecture hall, the floors of the clean rooms and on making various seismic pile caps and walls. The first steel structures and constructional walls of the new Feringa Building are now clearly visible.

Fitting out the labs

The furnishing of the laboratories in the Feringa Building has been awarded to the German company Wesemann. As this involves some 3 km of laboratory benches, 3,500 gas taps, 450 fume cupboards, 35 laser labs (class 3B and 4) and 9 climate and cold chambers, Wesemann will play a major part in the completion phase of the new University building. The criteria when awarding the contract were that the new labs must be of a high quality but must also be flexible, to keep pace with the dynamic nature of scientific research.

Wesemann is no stranger to the UG; they were also responsible for furnishing the labs in the Energy Academy Europe building and are involved in the current expansion of the lab facilities in the Linnaeusborg.

They will join contractors Ballast Nedam and De Groot-Lammerink Installatiecombinatie B.V. in the building team. The last tendering procedure will be completed in the autumn, when the contract for realizing the clean rooms will be awarded.

Modified building schedule

Despite the restrictions imposed by the coronavirus regulations, the first phase of the building work is going according to plan. There are, however, occasional problems with mutual coordination, the deployment of construction workers and the supplies of building materials. ‘During the completion phase in particular, we think that we will need more time to ensure that a lot of people can work together safely inside the building,’ explains Martin Kranenborg, project leader on behalf of the University. ‘In addition, the parties involved in a complex building project like the Feringa Building need more coordination time than we had anticipated.’ This means that the date for putting Phase 1 into use has been pushed back by around six months. The first three sections of the building (D-E-F) will now be ready for use in mid-2022. ‘I speak for all of the parties involved when I say that we are doing everything that we can to ensure that any delay in the completion of this project will be kept to an absolute minimum,’ continued Kranenborg. ‘But our focus is obviously on working carefully and delivering a high quality.’

Building Phase 1 (sections D-E-F) will be the first to be completed. These sections will be ready for staff from buildings 5117 and 5118 of Nijenborgh 4 to move into by mid-2022 (in accordance with the initial sliding plan). These two building wings can then be demolished so that Phase 2 can be realized.

Work on the next building sections B-C (Phase 1B) was started during Phase 1. Staff can only move into these sections when the installations from Phase 2 have been realized. Before Phase 2 (building section A) can be realized, building 5118 must be demolished.

Details of the removal plans will follow.

Source article and pictures: rug.nl